Park Derochie is proud to lead the scaffolding and coating work on the Keewatin Channel Bridge rehabilitation project in Kenora, Ontario. This essential infrastructure upgrade began in September 2025 and was completed by April 2026, ensuring the long-term reliability of one of the region’s most important transportation links.

PROJECT OVERVIEW

The Keewatin Channel Bridge, originally opened in 1939, underwent a comprehensive rehabilitation process to extend its service life and improve safety for thousands of daily commuters. The project also included work on the Portage Bay Bridge and this project finished in the fall of 2026. The completion of this vital connection between Keewatin and Kenora will provide an alternative route for drivers.

PROJECT PARTNERS

Owner: City of Kenora
Consultant: Stantec
Scaffold & Coating: Park Derochie Inc.
Steel Repairs: Ardy Rigging Ltd.
Special Thanks: Kenora Chiefs Advisory

A message from Kenora Chiefs Advisory:

“Kenora Chiefs Advisory is beyond grateful for the opportunity we have had to not only purchase and plan for a beautiful development on this property, but to do it in a true partnership with the hospital, the city, and our other partners. By working together fully on this and ensuring all needed voices are at the table.”

SCOPE OF WORK

The rehabilitation included:

  • Scaffolding & Access: Temporary access platforms and containment systems, including scaffold from a barge, a first for our team
  • Coating: Abrasive blasting and application of a three-coat system to all structural steel, using an ADI Abrasive Blasting Recycler to minimize hazardous waste
  • Environmental & Safety Measures: Pre- and post-job soil testing, sealed containments with negative air, hazardous waste testing for disposal

KEY HIGHLIGHTS

  • Scaffold Crew: Peaked at 25 workers, with innovative barge-based staging
  • Coating Crew: Peaked at 30 workers, implementing sustainable blasting technology
  • Access Solutions: Crews accessed the bridge by boat during open-water season; in winter, an ice road was developed and maintained to allow access from below
  • Community Impact: Maintaining traffic flowing while restoring critical infrastructure

INTERESTING FACTS

It may surprise some to learn that the Keewatin Channel Bridge is actually closer to our Edmonton office than to our Ontario office. It also represents Park Derochie’s second major winter bridge rehabilitation as a general contractor, building on experience gained during the Old Skeena Bridge project in Terrace, BC. Adding another layer of complexity, the Keewatin Channel is a busy summer waterway, meaning construction required careful planning around navigational clearances and visible signage to keep marine traffic moving safely. During the summer months, the waterway beneath the bridge buzzes with marine activity. In contrast, winter transforms the area into a network of snowmobile trails that run underneath it.


Together, these challenges showcase what Park Derochie does best: delivering critical infrastructure solutions in demanding environments. The Keewatin Channel Bridge project is more than a rehabilitation. It’s a continuation of our commitment to safety, precision, and thoughtful planning, even under the constraints of winter conditions and active waterways. By leveraging hard-earned experience and adapting to site-specific complexities, we’re helping ensure this vital connection remains safe and reliable for years to come.

Wins + Challenges

 

WINS

  • Barge-based scaffold
  • Reduced blasting waste
  • Strong teamwork

CHALLENGES

  • Seasonal access
  • Winter conditions
  • Active waterway

Conclusion

A message from Park Derochie: 

“Park Derochie would like to extend our sincere appreciation to all partners, crews, and community members who contributed to the success of the Keewatin Channel Bridge rehabilitation project. From innovative access solutions to working through challenging seasonal conditions, this project was made possible through strong collaboration, dedication, and a shared commitment to safety and quality. 

We are especially grateful to the residents of Kenora, Stantec, Ardy Rigging Ltd., Kenora Chiefs Advisory, and our highly skilled field teams whose expertise and professionalism helped bring this project to life. Your continued partnership and trust are what allow us to deliver critical infrastructure solutions in even the most demanding environments.”